Bitschnau Gleitschalung Slipform Forchheim 18 pieces of technology shafts and stairwells for Siemens Healthineers

Build time: 20 weeks in 2021
Height: 28,00 m
Slipform area: 22.850 m²
Concrete poured: 2.800 m³
Slipforming speed: m/day
Country: Germany

Client: Porr Industriebau GmbH